Building an Ohlone Tule Hut by
Adithya
Palle Troop
110, Fremont
|
|
I am Adithya Palle from Troop 110 and, with
my troop, I constructed the Tule House at Tule Ponds in Fremont. The
Tule House was a very rigorous project that took much more time than we
expected, but in the end, we were able to finish it through teamwork and
determination. The project consists of 3 parts, constructing the frame,
cutting and drying tules, and then attached the tules to the frame to
make layers around the house. Construction of the frame began on the
weekend of June 27 and was finished on the following weekend. This step
consisted of digging out holes for the frame, cutting down willows,
planting and cementing the willows in the ground, and llashing and
bending them together to form the dome shape. On the following weekends,
we focused on cutting Tules and attaching the layers at the same time,
but realized it would be much more effective if we simply cut tules
first and then attached the layers. After Tules are cut, they must be
dryed for one week before they can be attached to the house. Cutting
tules was definitely the most tedious part of the project as we needed
thousands to complete all the layers that were added. After the tules
were ready to be placed on, we held the tules against frame of the
house, and clipped them in place using more willow branches. We did this
process at 3 different levels on the frame to make 3 separate layers.
One of the most difficult parts of the project was flattening the final
layer at the top and attaching a cap to give the house a nice, rounded
look. After all of this was done, we attached a door frame at the
entrance for aesthetic purposes and cleaned up areas around the house
while adding some finishing details. On August 1, 2020 we finished up
the Tule House.
|
|
cutting tules |
making holes for support |
This project took 10 workdays that were
on average 6 hours long to complete with an average of 8 workers
everyday. I would like to thank all the adults and scouts of Troop
110 who spent dozens of hours working on this project till its
completion. Thank you to: Mr. and Mrs. Autenreith, Bailey
Autenreith, Trevor Autenreith, Mr. Oates, Ethan O’ Neil, Lalith
Sasubilli, Mr. Sasubilli, Ayush Sharma, Mr. Sharma, Vedh
Janardhanan, Suchir Sreevathsa, Mr. Sreevathsa, Tilak Patel, Aariv
Iyengar, Ben Weavil, Nick Weavil, Raghav Karra, Mr. Karra, Neil
Shah, Mr. Shah, and Shiva Palle.
.
|
|
securing structure |
finishing roof |
I
|